![[GEGS logo]](Gegs4.gif)
Periodic
Electrical Inspection
|
- extent - costs - reports - guidance -
Much has been said about the requirements of the Electricity at Work Regulations in relation to Portable Appliance Testing, and the need to have competent qualified electricians carrying out maintenance or new work on electrical installations. What seems to get ignored is the need for Periodic Inspection and Testing of all electrical installations.
The IEE Wiring Regulations (BS 7671) require that Periodic Inspection and Testing of electrical installations is carried out at such intervals as are consistent with the type of installation, its use and operation, the frequency of maintenance, and the external influences upon it.
Sensible time scales, that will give an idea of the sort of thing that is being looked for, are as follows:
The main aim of this note is not to persuade you that the Periodic Inspection and Testing has to be done nor to point out the timescales for having it done. With the point made above, I am taking that as read.
The aim is to help you to set about getting it done.
- introduction - costs - reports - guidance -
When entering into an agreement for the Periodic Inspection and Testing of a building under your control it is a fundamental requirement that the extent and limitations of the inspection and testing be fully described for the contractor. It is recommended that the following procedures are adopted and that the relevant points be discussed with the contractor prior to completing the agreement documents.
- introduction - extent - reports - guidance -
If must be realised that it is extremely difficult to place a finite value on work that is, by its very nature, an unknown quantity. There are many factors that can affect the time that may be taken to carry out a proper examination of the installation so it is important that provision is made for the contractor making an extra charge for any unforeseen work, particularly out of hours working, that may arise during the course of the work, to enable a reasonably thorough inspection and test to be conducted and a comprehensive report to be provided.
- introduction - extent - guidance -
On completion of the Inspection a report should be provided by the contractor, detailing, to the best of their knowledge and belief, the condition of the installation, results of all tests carried out, a list of recommendations and a conclusion as to whether the installation is safe to use in its present state. If the conclusion drawn is that the installation is unsafe, then the supply should be switched off and notices placed warning of the danger before the contractor leaves site.
- introduction - costs - extent -
The following is offered as guidance as to what should be requested from the contractor. It should be noted that this guidance is by no means exhaustive, and any special local conditions or requirements should be taken into account when determining the work.
Nature of installation and requirements for test.
The inspection of the installation indicated has been requested because it is Mandatory / Recommended.
The contractor must be advised as to the extent of the inspection and tests to be carried out. These will be either:
N.B. The test sequence will include testing of every main and sub-distribution board and final sub-circuit.
The following is guidance on the extent of the work that should be done.
Check for any obvious mechanical damage or deterioration of materials and equipment, exposed cables and live parts, missing covers, fixings, labels and notices etc.
N.B. This procedure will not necessitate switching off the installation.
Repeat as for Visual Inspection Only but also include a thorough inspection of:
This should include removing light fitting covers, switch plates, socket outlets and covers of equipment.
A sample of approximately 10% of all parts and areas of the installation should be inspected.
N.B. Actual % to be agreed with yourselves.
The following tests, as prescribed in IEE Guidance Notes, should be carried out where practicable.
As Visual Inspection Supplemented By Testing with the addition of providing information in accordance with IEE Regulation 514-09-01. This should include the provision of distribution board schedules. schematic diagrams and as installed drawings detailing the position of fixed equipment.
- introduction - extent - costs - reports - guidance -
GEGS is listed on Chartered Consultant