![[GEGS logo]](Gegs4.gif)
![]()
![]()
Periodic
Electrical Inspection
|
- extent - costs - reports
- guidance -
Much has been said about the requirements
of the Electricity at Work Regulations in relation to Portable
Appliance Testing, and the need to have competent qualified electricians
carrying out maintenance or new work on electrical installations. What seems to
get ignored is the need for Periodic Inspection and Testing of all electrical
installations.
The IEE Wiring Regulations (BS 7671)
require that Periodic Inspection and Testing of electrical installations is
carried out at such intervals as are consistent with the type of installation,
its use and operation, the frequency of maintenance, and the external
influences upon it.
Sensible time scales, that will give an
idea of the sort of thing that is being looked for, are as follows:
Office Buildings :- 5 yearly
Retail Premises :- 3 yearly
Swimming Baths :-Annually
The main aim of this note is not to
persuade you that the Periodic Inspection and Testing has to be done nor to
point out the timescales for having it done. With the point made above, I am
taking that as read.
The
aim is to help you to set about getting it done.
- introduction - costs - reports
- guidance -
When entering
into an agreement for the Periodic Inspection and Testing of a building under
your control it is a fundamental requirement that the extent and limitations of
the inspection and testing be fully described for the contractor. It is
recommended that the following procedures are adopted and that the relevant
points be discussed with the contractor prior to completing the agreement
documents.
Determine your requirements for
inspection and testing and tailor the procedures accordingly.
Agree before commencing the work the
amount of down time that can be tolerated and arrange a provisional programme
for switching off:
·
totally.
·
individual
areas or distribution boards.
It is important that these times are
confirmed immediately prior to the contractor switching off.
As it is neither practical nor possible
to inspect all parts of the installation, a sampling process will be employed,
normally in the order of 10% of all accessories, lighting fittings and control
equipment.
Detail any limitations of the inspection
and testing to be carried out and explain that the installation must not be
dismantled in any way other than opening equipment covers, and that the
building structure must not be disturbed. This means that concealed cables and
equipment will not be inspected.
Identify any new parts of the
installation that may not need to be included in the work.
- introduction - extent - reports - guidance -
If must be
realised that it is extremely difficult to place a finite value on work that
is, by its very nature, an unknown quantity. There are many factors that can
affect the time that may be taken to carry out a proper examination of the
installation so it is important that provision is made for the contractor making
an extra charge for any unforeseen work, particularly out of hours working,
that may arise during the course of the work, to enable a reasonably thorough
inspection and test to be conducted and a comprehensive report to be provided.
- introduction - extent - guidance -
On completion of the Inspection a report should be provided by the contractor,
detailing, to the best of their knowledge and belief, the condition of the
installation, results of all tests carried out, a list of recommendations and a
conclusion as to whether the installation is safe to use in its present state.
If the conclusion drawn is that the installation is unsafe, then the supply
should be switched off and notices placed warning of the danger before the
contractor leaves site.
- introduction - costs - extent
-
The
following is offered as guidance as to what should be requested from the
contractor. It should be noted that this guidance is by no means exhaustive,
and any special local conditions or requirements should be taken into account
when determining the work.
Nature
of installation and requirements for test.
The
inspection of the installation indicated has been requested because it is
Mandatory / Recommended.
The
contractor must be advised as to the extent of the inspection and tests to be
carried out. These will be either:
Visual Inspection Only; or
Visual Inspection Supplemented By
Testing; or
Survey, Visual Inspection Supplemented
By Testing
N.B.
The test sequence will include testing of every main and sub-distribution board
and final sub-circuit.
The
following is guidance on the extent of the work that should be done.
Check
for any obvious mechanical damage or deterioration of materials and equipment,
exposed cables and live parts, missing covers, fixings, labels and notices etc.
N.B.
This procedure will not necessitate switching off the installation.
Repeat
as for Visual Inspection Only but also include a thorough inspection of:
The main switchgear and all distribution
boards. These should be inspected for the following:
·
Fuses and MCBs
are correctly rated for over-current and fault current
·
Fuse and
switch contacts are clean and have not been over-heating
·
Conductor
terminations are tight and correctly lugged (if possible)
·
Busbar connections
are properly made and clamps are tight.
Cables - whenever possible cables should
be inspected to ascertain:
·
The
suitability for the load and operating environment
·
The condition
of the insulation and protection
·
Adequacy of
fixings and mechanical protection
·
Suitability of
glands and shrouds
·
Proper use of
earthing rings and earth connections
·
Any signs of
over-heating and damage.
Equipment, accessories and lighting
fittings should be inspected for:
·
Deterioration
due to the atmosphere, mechanical damage, over-heating and adequate fixings.
·
Connections of
conductors and condition of flexes.
This
should include removing light fitting covers, switch plates, socket outlets and
covers of equipment.
A
sample of approximately 10% of all parts and areas of the installation should
be inspected.
N.B.
Actual % to be agreed with yourselves.
The
following tests, as prescribed in IEE Guidance Notes, should be carried out
where practicable.
Continuity of circuit protective
conductors (CPCs) at all metal accessories and equipment within a height of 3.5
metres from floor level, and at 10% of all lighting fittings.
Continuity of all bonding conductors and
earth clamps.
Continuity of all ring circuit
conductors, including CPOS.
Insulation resistance between live
conductors and earth of all circuits collectively, excepting any circuits
supplying electronic equipment which may be damaged by the test. These shall be
listed separately as not having been tested.
An electrical separation test on all
electrically separated circuits.
Polarity at the board and at a 10%
sample of all lighting switches and equipment to ensure that switches interrupt
only phase conductors.
Earth fault loop impedance (Ze) at the
main intake position.
Earth fault loop impedance (Zs) at each
distribution board.
Earth fault loop impedance (Zs) test on
every final circuit and every socket outlet.
Test all Residual Current Devices.
The resistance of every earth electrode.
Prospective fault current at the main
intake position and at every distribution board.
A manual operation test on all MCBs,
RCDs, switch fuses and isolators.
As
Visual Inspection Supplemented By Testing with the addition of providing
information in accordance with IEE Regulation 514-09-01. This should include
the provision of distribution board schedules. schematic diagrams and as
installed drawings detailing the position of fixed equipment.
- introduction - extent - costs
- reports - guidance -

Telephone
+44
(0)1480 471733
FAX
+44
(0)1480 393955
Postal address
1
Avenue Road, St Neots, Cambs.